- Enlarge the existing wall opening (wider and taller) and install the homeowner-provided medicine cabinet
- Labor and cutout only — cabinet supplied by homeowner
- Small repair section, 16" wide × 6' tall, smooth finish
- Seal the 2 small openings at the old washer/dryer hook-up location
- Paint not included
- Remove the damaged top particle-board layer only (hall bath; 2 layers exist)
- Install a new plywood subfloor layer built to the surrounding floor height
- Flooring itself remains covered by Invoice #340
- Remove the existing damaged vanity
- Install the homeowner-provided replacement (same size) with faucet and supply/drain hook-up
- Remove and reinstall
- Covered by Invoice #340 — no charge on this change order
- Bath fixture and flooring-layer removal in the hall bath; runs with the original demo
- Covered by Invoice #340 — no charge on this change order
Optional — not included in the totals below. If approved: tub total becomes $4,400.00, shower total becomes $4,100.00.
| Medicine Cabinet | $200.00 |
| Drywall — small section + seal 2 holes | $350.00 |
| Subfloor — top layer + new plywood | $450.00 |
| Vanity — remove, install owner's + faucet | $250.00 |
| Toilet — remove & reinstall | $150.00 |
| New Tub with Surround Insert (Option A) | $1,800.00 |
| General Conditions — included (Invoice #340) | $0.00 |
| Demo & Trashout — included (Invoice #340) | $0.00 |
| Total — New Tub Option (Est #1321) | $3,200.00 |
Check is a preferred method. Credit card accepted via the Plastiq payment link in the Terms below.
This is Change Work Order #1 on accepted Invoice #340 — 3 Lighthouse Drive, Hampton, VA. (New Tub option) SCOPE OF WORK 10115 Cabinet: Enlarge the existing wall opening (wider and taller) and install the homeowner-provided medicine cabinet — labor and cutout only, cabinet supplied by homeowner. 10107 Drywall: Small repair section 16" wide × 6' tall, smooth finish; seal the 2 small openings at the old washer/dryer hook-up location. Paint not included. 10117 Flooring — Subfloor: Remove the damaged top particle-board layer only (hall bath; 2 layers exist) and install a new plywood subfloor layer built to the surrounding floor height. Flooring itself remains covered by Invoice #340. 10120 Plumbing: Remove the existing damaged vanity; install the homeowner-provided replacement (same size) with faucet and supply/drain hook-up. Remove and reinstall toilet. [FIXTURE: New tub (similar size) with tub surround insert — tub install, tub drain, connection to the upgraded shower valve, new drain line if needed.] 10100 General Conditions: INCLUDED — no charge (covered by Invoice #340). 10101 Trashout: INCLUDED — no charge (covered by Invoice #340). OWNER SUPPLIES: replacement medicine cabinet and vanity (delivered to jobsite before install). CONTRACTOR SUPPLIES: plywood subfloor layer, drywall materials, tub with surround insert, plumbing fittings and drain line. NOT INCLUDED: LVP flooring install (covered by Invoice #340), paint, structural/engineering work, permits. Optional add-ons (not included in the total): interior doors (3) with frames — $1,200.00 (performed only if approved). TERMS AND CONDITIONS By agreeing to these Terms and Conditions, the customer acknowledges and accepts the outlined responsibilities and scope of work. Notes: **Jobsite will be left clean once completed. **Contractor is not responsible for damage caused inside the home while repairing the foundation. Warranty: **12 months workmanship. Payment Terms: Total Project Cost: $3,200.00 Deposit to Schedule: $1,600.00 Final Payment: $1,600.00 Check is a preferred method. **You can pay by credit card using the link below. https://request.plastiq.com/pay-tidewater-home-improvement-llc Cards not eligible for payment: - Virtual Affirm credit card