Change Work Order #1 — Scope of Work & Estimate
09/03/2026
Change Work Order #1
$4,400.00 — New Tub Option
3 Lighthouse Drive · Hampton, VA 23664
On Accepted Invoice #340 · Additional Bathroom Work
View PDF — Tub Option PDF follows the selected option · Valid until October 3, 2026
Project Overview
CustomerBrian Glodt
ProjectChange Work Order #1 — Hall Bath
Address3 Lighthouse Drive, Hampton
Base JobInvoice #340 · $4,051.75
Base Paid$2,025.87 received (9/2)
New FixtureNew Tub + Surround Insert
Pick Your Bathroom Option — Tub or Walk-In Shower (either/or)
OPTION A
New Tub with Surround Insert
New tub (similar size) with tub surround insert (no tile) — tub install, tub drain, connection to the upgraded shower valve, new drain line if needed.
$1,800.00 added to the work below
Wave Estimate #1324
OPTION B
Walk-In Shower Insert
Walk-in shower base and surround insert (no tile, no tub) — install, shower drain, connection to the upgraded shower valve, new drain line if needed.
$1,500.00 added to the work below
Wave Estimate #1325
Only one of the two options applies — select the one you prefer. Everything below is the same for either choice. If you are not sure yet, tell us and we will keep both prices available.
Included Scope (same for both options)
10115Medicine Cabinet$200.00
  • Enlarge the existing wall opening (wider and taller) and install the homeowner-provided medicine cabinet
  • Labor and cutout only — cabinet supplied by homeowner
10107Drywall Repair$350.00
  • Small repair section, 16" wide × 6' tall, smooth finish
  • Seal the 2 small openings at the old washer/dryer hook-up location
  • Paint not included
10117Subfloor$450.00
  • Remove the damaged top particle-board layer only (hall bath; 2 layers exist)
  • Install a new plywood subfloor layer built to the surrounding floor height
  • Flooring itself remains covered by Invoice #340
10120Vanity$250.00
  • Remove the existing damaged vanity
  • Install the homeowner-provided replacement (same size) with faucet and supply/drain hook-up
10120Toilet$150.00
  • Remove and reinstall
10100General ConditionsINCLUDED
  • Covered by Invoice #340 — no charge on this change order
10101Demo & TrashoutINCLUDED
  • Bath fixture and flooring-layer removal in the hall bath; runs with the original demo
  • Covered by Invoice #340 — no charge on this change order
Site Photos
10109Interior Doors (3) — 32"$1,200.00
  • Interior doors with frames, 32" — 2 left-hand, 1 right-hand
  • Re-square the frames and replace the doors
Estimate
Medicine Cabinet$200.00
Drywall — small section + seal 2 holes$350.00
Subfloor — top layer + new plywood$450.00
Vanity — remove, install owner's + faucet$250.00
Toilet — remove & reinstall$150.00
Interior Doors (3) — 32", 2 left + 1 right$1,200.00
New Tub with Surround Insert (Option A)$1,800.00
General Conditions — included (Invoice #340)$0.00
Demo & Trashout — included (Invoice #340)$0.00
Total — New Tub Option (Est #1324)$4,400.00
Payment Schedule — 50 / 50
Draw 1 — Deposit to Schedule
50%
$2,200.00
Draw 2 — Final Payment
50%
$2,200.00

Check is a preferred method. Credit card accepted via the Plastiq payment link in the Terms below.

Terms & Conditions

This is Change Work Order #1 on accepted Invoice #340 — 3 Lighthouse Drive, Hampton, VA. (New Tub option - interior doors included) SCOPE OF WORK 10115 Cabinet: Enlarge the existing wall opening (wider and taller) and install the homeowner-provided medicine cabinet — labor and cutout only, cabinet supplied by homeowner. 10107 Drywall: Small repair section 16" wide × 6' tall, smooth finish; seal the 2 small openings at the old washer/dryer hook-up location. Paint not included. 10117 Flooring — Subfloor: Remove the damaged top particle-board layer only (hall bath; 2 layers exist) and install a new plywood subfloor layer built to the surrounding floor height. Flooring itself remains covered by Invoice #340. 10120 Plumbing: Remove the existing damaged vanity; install the homeowner-provided replacement (same size) with faucet and supply/drain hook-up. Remove and reinstall toilet. [FIXTURE: New tub (similar size) with tub surround insert — tub install, tub drain, connection to the upgraded shower valve, new drain line if needed.] 10109 Doors & Trim: Interior doors with frames (32in) — 2 left-hand, 1 right-hand. Re-square frames and replace doors. 10100 General Conditions: INCLUDED — no charge (covered by Invoice #340). 10101 Trashout: INCLUDED — no charge (covered by Invoice #340). OWNER SUPPLIES: replacement medicine cabinet and vanity (delivered to jobsite before install). CONTRACTOR SUPPLIES: plywood subfloor layer, drywall materials, tub with surround insert, 3 interior doors with frames (32in), plumbing fittings and drain line. NOT INCLUDED: LVP flooring install (covered by Invoice #340), paint, structural/engineering work, permits. TERMS AND CONDITIONS By agreeing to these Terms and Conditions, the customer acknowledges and accepts the outlined responsibilities and scope of work. Notes: **Jobsite will be left clean once completed. **Contractor is not responsible for damage caused inside the home while repairing the foundation. Warranty: **12 months workmanship. Payment Terms: Total Project Cost: $4,400.00 Deposit to Schedule: $2,200.00 Final Payment: $2,200.00 Check is a preferred method. **You can pay by credit card using the link below. https://request.plastiq.com/pay-tidewater-home-improvement-llc Cards not eligible for payment: - Virtual Affirm credit card